Utilities, Blar Mhor Phase 2

Client: Highland Council

Location: Blar Mhor ph2

Design team

Kevin O’Hare

Project duration

5 days

Project overview

  • Design Drawing
  • Phase 2 consisted of laying 180mm hppe pipe, 125mm hppe pipe and 63mm mdpe pipe
  • 2nr pressure test and sample of newly laid main
  • Once passed, Scottish Water carried out tie-in of newly laid 180mm main to their existing 180mm hppe main
  • After connection, there were 63nr 32mm connections carried out