Fishnish Pier, Isle of Mull

Client: Forestry Commission Scotland

Location: Fishnish, Isle of Mull

Project duration

48 weeks

Project overview

The project involved the construction of a steel combi-pile commercial pier, complete with an access road and hardstanding, at a former mineral extraction site on Mull to facilitate the export of round timber.

The project included:

  • Pre-construction particulate and noise surveys to protect a nearby salmon farm.

  • Construction of an access road and hardstanding area.

  • Driving 1,200mm diameter steel combi-piles to form the pier structure.

  • Installation of 920m of Macalloy tie bars to secure the pile walls.

  • Infilling the combi-piles with structural grade concrete.

  • Installation of precast concrete copes, general infill, and surrounding rock armour.

  • Fitting of anodes for cathodic protection to the outer wall in the tidal zone.

  • Final surfacing with of ready-mix concrete and installation of a weighbridge after a one-year settlement period.

Key challenges and successes

To significantly reduce costs, 30,000 m³ of rock was blasted at a nearby site, saving the client considerable expense on aggregates and transportation. The material was processed on-site using crushers and screeners to produce specified 6A fill, which was used to fill to the mid-tide level. This work was conducted while also monitoring and repositioning piles that had experienced slippage on the rockhead.