Client: Highlands and Islands Enterprise
Location: SAM complex, Dunbeg
Key consultants
- Fowler MacKenzie
- Profile projects
- Green roof
- SR Young
Project duration
60 weeks
Project overview
Construction and delivery of a new marine resource centre for HIE, consisting of 7 research spaces aimed at the startup market and smaller companies.
Key challenges
Location and size of the site with limited space for storage of plant and materials.
Key successes or innovations
Last minute design change due to the Metsec needing to be fixed directly to the teel, meant that had three days to paint the steel work prior to its delivery to site.