Accommodation Units, Isle of Iona

Client: The Iona Community Trust

Location: Isle of Iona

Project duration

70 weeks

Project overview

This project involved the comprehensive internal and external refurbishment of the north, east, and west wings of the Abbey estate. The work focused on modernising all guest, staff, and communal facilities while also carrying out essential upgrades to the building’s historic windows and external doors.

The project included:

  • Complete internal refurbishment of all guest and staff accommodation units.

  • Refurbishment of the communal refectory, server, and catering areas.

  • Extensive refurbishment of the existing sash and case windows.

  • Replacement of the external entrance doors for each of the three wings.

Key challenges and successes